Project Requirements

  • Sustainable design and an aggressive design/construction schedule were all required on this landmark project which achieved LEED Gold Certification

What ACCO Delivered

During the early portion of the construction phase, ACCO's design-assist role evolved into a design-build partner alongside Turner, ACM and other specialty trades. Thanks to the coordination and critical planning provided by our engineering and construction departments, ACCO was able to complete the HVAC design, obtain a permit and install our systems ahead of schedule.

A major challenge on the project was that construction had to begin prior to completion of the design. Compounding this challenge were the numerous owner changes that occurred during construction. Thanks to the combined efforts of Turner, ACM, and ACCO these changes were incorporated into the design and construction while maintaining critical milestone dates.

The project included a 3000-ton central chilled water plant, a 6000 Ton-Hr TES tank and a 14,000 MBH central heating plant. Chilled and hot water piping was distributed to 1100 fan coils and 950,000 CFM of air handlers.  In slab radiant heating and cooling systems were provided for the plaza level and sky lobbies.

Project Team

Owner: Hanjin International & Korean Airlines

Architect: AC Martin Partners

General Contractor: Turner Construction

Mechanical Engineer: ACCO Engineered Systems

Mechanical Contractor: ACCO Engineered Systems