Confidential Data Center Phase 2 | McCarran, NV

    This project is a multi-phase greenfield site in Storey County, Nevada. Minimal project specifics can be shared due to a nondisclosure agreement.

    PROJECT FEATURES

    • HVAC & Plumbing
    • Large scale project completed through ACCO’s remote and local operations

    PROJECT SUMMARY

    ACCO was selected on a best value basis for this 30MW Data Center that included 8,600 tons of cooling, raised platform dry cooler yard and fuel oil distribution piping servicing (15) 3250kW generators. Project was fully commissioned through L5 using BIM 360 Field.

    Over approximately 15 months, by making extensive use of prefabrication and partnership with the local labor unions, ACCO installed HVAC, plumbing and process systems totaling over 138,000 manhours.

    All fabrication was produced in ACCO shops in Sacramento and Reno and shipped to the jobsite. This accounted for over 80% of weld inches on the project.