The Forum Renovation | Los Angeles, CA

    The project is a renovation of the Great Western Forum, former home to the Los Angeles Lakers and Kings built in 1967. The Madison Square Garden Company purchased the building and surrounding parking to renovate the venue for concert events.

    Khosla Ventures: a venture capital firm run by people who listen to, analyze, and advise entrepreneurs, manages the main fund that supports early and late stage investments and a seed fund for developing very early-stage experiments.  As a firm that focuses on next-generation energy projects, new materials, mobility, the Internet and silicon technology, it was imperative that the building reflects these industries.

    Project Requirements

    The project required a fast-track renovation schedule that overhauled the complete building from roof to parking in just 8-months. It required full-time on-site project management to make the correct decisions on an hour to hour basis. Our crews worked over-time and shift work to complete the interior HVAC renovations on schedule for the opening event with The Eagles.

    What ACCO Delivered

    ACCO was responsible for the HVAC renovations which included refurbishing the two 216,000 CFM central air handling units for the concourse and bowl seating, which included new variable speed drives for the fans, rebuilt fan and coil section, new liner and sound trap assemblies. Four new custom variable volume air handling units were added to feed air conditioning to previously unconditioned areas of the building and new spaces such as the Chase Lounge, Forum Club and Star Dressing Rooms. The central plant renovation included a new 550Ton replacement chiller for the bowl and concourse areas and a new 150-Ton scroll chiller and tower for the new air handling systems. Boilers and heating hot water systems were renovated for makeup water and gas train piping. Split systems were added for new 24/7 critical load rooms that housed all the new audiovisual, electrical and telecom. The roof work included replacement fans for the seating area and a new pyrotechnic smoke purge exhaust fan system.

    Project Team

    Owner: Madison Square Garden Company
    Architect: BBB Architects
    General Contractor: Clark Construction
    Design-Build criteria Consultant & Commissioning Agent: ME Engineers
    Design-Build Mechanical/Controls: ACCO Engineered Systems